Forum Replies Created

Viewing 3 posts - 1 through 4 (of 4 total)

  • RE: View to show calculated column

    Many thanks Lutz, your solution works great.

    Andre your solution nearly works but Tasks 6 and 7 are shown as green and not null.

  • RE: View to show calculated column

    LutzM (4/1/2012)


    Shouldn't be Task4 show Amber then? (It's "between" amber and green)

    No, it needs to take the colour above as it hasn't got to the amber colour yet.

    What I want...

  • RE: View to show calculated column

    LutzM (4/1/2012)


    Why should Task2 return Amber?

    Why NULL for Task 6 and 7?

    Task 2 is amber as it is one day old, so between red and amber.

    Tasks 6 and 7 are...

Viewing 3 posts - 1 through 4 (of 4 total)