DJH-445911 (5/12/2014)
Thank you for the replies.OK so let it run unless there is a reason to re-initialise. Thank you.
And I can take a full backup at any time and it wont affect the log shipping?
correct
In that case in the event of us needing to do a point in time restore, I could take the previous nights full backup + subsequent log backups (that would have been log-shipped to our remote site)?
Also correct. Your log backups will still be on the primary as well if you set the retention period long enough (> 1 day at least).
If you do restore your primary to a previous time you would have to reinitialise log shipping then.
---------------------------------------------------------------------