sneumersky (7/12/2013)
If I am not mistaken, using one execute package task (EPT) within a loop would execute the packages serially, right? Parallel EPT execution would require multiple EPTs that were not connected to each other.
You're right, that would be needed. 4 EPT tasks would be a good start I think.